Project Highlights
- Managed a frantic schedule and ever-expanding scope of work to complete the project two weeks ahead of schedule
- Accommodated tenant lease agreements by delivering on uncompromising deadlines for customized installations
- Proficiently redeployed manpower to rapidly wire sections under roof due to delays in roof installation
- Saved more than $100,000 in budget by modifying/optimizing fire alarm/power
- Collaborated with Taubmann IT to design optimal low voltage for phone/data/internet
“When you consider that PayneCrest effectively managed three turnover dates and accelerated tenant completion schedules, the Taubman project is a model of ‘best practices.’”
— Carl L. Groeshen, owner/construction manager, Project Delivery Resources, LLC