Project Highlights
- Compressed 12-week schedule to deliver mission critical components to activate data center
- Installations included power, data, voice, fiber, multi-pair and coax cabling covering 35,000 square feet of raised floor.
- Additional infrastructure installations included 8,300 data cables totaling 91 miles, 3,000 fiber strands, 120,000 feet of voice cables and 200,000 feet of #10 THHN building wire.